Why Can't Developers Estimate Time?
- hsmyers 15y agoNicely complicated--- useful if the boss or client wants verbiage. If asked directly though, I usually say "If I've done it before, I know how long it takes; if not then not."
- ashleymoran 15y agoHaha, yes. That is the bottom line. But once they ask "why?", then OMG, worms everywhere! My post is definitely not suitable for most management, but in a discussion with a bunch of fellow geeks, it did fit in with the discussion. Explaining this to management/clients is not easy. It's a problem that needs tackling, but it's a separate problem.
- oceanician 15y agoIt's because developers are rubbish for not being pyshic ;) I'm always suprised how few estimates take account of environmental contributions!!
- ashleymoran 15y agoRe "environmental contributions", that was part of the discussion, but thinking about it - estimating total effort and elapsed calendar time are very different!
- oceanician 15y agoelapsed calendar time and total effort are often the same in a customer's mind. Time is actually money.
- ashleymoran 15y agoThis is why Kanban and its focus on lead time is more valuable than Scrum and its focus on velocity, IMO.
- allenp 15y agoIt's because developers are eternally optimistic. How else can you explain someone hitting a "compile" button a hundred times a day, hoping each time to get no errors?
- qntm 15y agoHey, sometimes I compile with the expectation of error, just to make sure that the right error comes out.
- aycangulez 15y agoThe author refers to Don Reinertsen who is a proponent of kanban in software development. For a brief explanation of kanban and how it can help improve estimation, see: http://flow.io/how-kanban-can-help-you-increase-your-teams-capacity.html http://flow.io/how-kanban-can-help-you-increase-your-teams-c...
- ukaszg 15y agobecause they actually try to give truthful answers, instead of making up numbers like everyone else.
- gulbrandr 15y agoI think no one can estimate time, not just developers.
- btilly 15y agoI prefer to take my advice from someone who has demonstrated the ability to repeatedly run projects and estimate them in advance to surprisingly high accuracy. I therefore recommend Software Estimation by Steve McConnell, available at http://www.amazon.com/Software-Estimation-Demystifying-Practices-Microsoft/dp/0735605351/ref=sr_1_1?ie=UTF8&qid=1302269835&sr=8-1-spell http://www.amazon.com/Software-Estimation-Demystifying-Pract....
- ashleymoran 15y agobtilly, thanks for the reference to this. I've added it to my Goodreads list.
- deleted 15y ago[deleted]
- netghost 15y agoIf you like Steve McConnell's work, you should take a look at http://www.LiquidPlanner.com http://www.LiquidPlanner.com, we built our entire product around the notion of ranged estimation so that your schedule actually captures some of uncertainty involved in estimation. Also if anyone wants some more good books to read we have a list of some of our favorite project management books at http://www.liquidplanner.com/recommended-reading http://www.liquidplanner.com/recommended-reading.
- TimLangley 15y agoGood post Ash (good to see the discussion being consolidated) IMHO - it's usually due to the lack of "up front planning" by Managers / Analysts. If you compare building software to more general "building endeavors" (for example building the Olympic stadium) then, IMHO, developers are really the "construction workers" (the people actually doing the work). However no intelligent Olympic committee would countenance starting work without (for example) an architect making an incredibly detailed plan (and even a working replica model). IMHO the problem we suffer from as developers is most often diving in too fast because: a) we're the construction workers b) when we do use Architects they are "construction workers too" (as opposed to being a trained with 'different but complimentary skills - it would be hard to imagine Sir Norman Foster laying bricks)
- zb 15y agoNo! That was the orthodoxy for 40 years and it got us nowhere, because the construction metaphor is fundamentally wrong.
- codelion 15y agoMay be because software development is a creative process or the same reason why Artists won't tell you how long they will take to finish a painting or Authors repeatedly miss publisher deadline for books.
- deleted 15y ago[deleted]
- wladimir 15y agoI do agree with him. In my opinion, software development is exactly a creative process. Many times, you have to come up with a creative solution that fits within certain constraints. Also, in the beginning usually only a vague image is known. The artist (developer) has to fill this in and make sure it is what the client wants. Also, many creative works are collaborative efforts as well these days. I'm not sure how that changes anything. If anything, it makes estimates harder.
- VMG 15y agoThe same thing has to be done in engineering. Just because creativity is involved doesn't make programming an art. Art can break rules and you can sell weird color splotches for millions, but the output of your /dev/random will always be worthless.
- wladimir 15y agoYou could equally say "Just because math is involved doesn't make it engineering". But I suppose it's something in between art and engineering. With regard to "sell weird color splotches for millions" - Isn't that the same with code? You can sell a simple game or app to millions of people and become rich. The amount of money you earn doesn't have any connection to complexity.
- VMG 15y agoYou are right, there is a sub-gendre of entertainment software that does have similarity to art. But even there you'll never buy a product because it crashes, while a work of Art can be valuable because it is ugly
- Lozzer 15y agoI estimate by considering an optimistic, pessimistic and normal value for each task. I then have a spreadsheet that does a modicum of statistical analysis to give you times against probability that the task will be finished. Some of the benefits I find are: 1. Getting into the pessimistic mindset helps produce better estimates 2. Tasks with a large spread are things you aren't really clear about, and are an obvious target to be attempted first 3. Giving a range of values to the person asking for the estimate seems to help them remember it is an estimate.
- ctdonath 15y agoNeed to include "tasks which will take significant time but I can't tell you what they are because we won't know until we get there". Managers can't seem to deal with the notion that 10-30% of a project is completely unknown when writing initial schedules.
- Maro 15y agoThere are human timescale factors involved. If you give an estimate that's too far out, it'll be outside your client's planning scale. That means it's so far out, she doesn't know what will happen by then, she won't do the project. In my experience, this is scale is roughly 9-12 months, unless you're dealing with a MegaCorp. So most estimates end up at 6-9 months, which then slip into 9-12 territory, and hopefully not much further =) In my experience, coding time is usually easy to estimate, and that's what most estimates coming from developers should be taken to estimate. But then you have integration (nothing works), testing (everything is broken), and then realizing what the client meant when she said X (solved the wrong problem, optimized for wrong features), those are the tough ones. You should take the estimate for coding time (coming from the developer), and multiply that at least by 2x. Of course, going back to my original point, that estimate may be outside the "human timescale", so you may not be able to tell the client that... So, to answer your original question, developers can estimate primary development time up-front pretty well, but they suck at estimating integration, testing and shipping time. A related thing I noticed is that if you ask a developer during the late(r) stages of the project when she'll be finished with the "next stable version", the answer usually hovers around "in 2 weeks", even if the actual answer is more like 3 months. The developer isn't lying, she genuinely believes that it can be done in 2 weeks. That's why you want experienced engineers and not fresh college grads leading teams and giving estimates. They've gone through these experiences, have a lot of soft data metrics in their heads, and can come up with good multiplicative factors. I'd be curious if orgs like Google have a database of project data to aid planning.
- HeyLaughingBoy 15y agoshe genuinely believes that it can be done in 2 weeks This is where having good historical records is useful. If I have done 2 similar tasks before and they took a month each, then a 2-week estimate has no validity. As far as general code estimation goes, lines of code and complexity taken together form a pretty good metric. If I estimate I have to write 50 lines of high-performance multithreading code, I might say it will take 8 hours. If it's 50 lines of fizzbuzz, estimate drops to 1 hour. But like you say, that's just coding (and unit test). The full task probably requires (1) getting or understanding requirements, (2) at least some cursory thought about design and (2a) having a hallway review with somene if you're not sure. Then when we're done with code, unit test (don't forget to estimate how long it will take to create, debug and run the tests) and Code Review (how many reviewers do you need, how long will it take them to get around to inspecting your code, etc), someone has to estimate (4) how long the test team will take to write test cases and do the system test of the new feature, (5) tech docs has to update the user manuals, (6) sysadmin or the Release Master estimates how long deployment will take. In short, at least in the environment I work in, that 50 lines of code that took eight hours to write, will easily require an entire week before any customer can see it. In my experience, it's often not so much that the developer didn't estimate accurately how long coding would take, it's that the developer never thought about all the ancillary tasks that have to be done (code review, unit test, documenting the design changes, etc), so they were not in the estimate.
- Muchi 15y agoYou don't know the problems/limitations you will run into until you begin working on your project. We have immersed ourselves in a culture where it's expected to estimate the unknown.
- JoeCortopassi 15y agoBecause developers don't work in a vacuum. The second you estimate the project, the client starts changing it...
- bsaunder 15y agoAlmost all bad estimates are due to a lack of information. In software development, the information that tends to be missing are the particulars of the task being estimated (which code needs to be modified, in what way). This missing information is highly unique and not to generally transitive from one programing assignment to the next. Additional information about the process is usually not the problem. Things like CMM tend to focus on the process information rather than the particulars of the coding problem at hand. Which, leads many developers to think: "You're doing it wrong."
- vermasque 15y agoSpeaking from experience at a large multi-year project at a BigCo, I am quite familiar with the failures of estimation. Some information is absent because some things are simply unknown due to inexperience or inability to predict future changes or mistakes (reasonable). However, other things are lacking because there is no motivation or demand to produce them. For example, waterfall processes generally throw the software development lifecycle on a schedule for a system or subsystem: requirements, design, implementation, test. If the lifecycle stages are not divided into tasks upfront (which then should be further divided), then the complexity of each stage is basically not being factored into the estimates for each stage. This is setting the stage for failure unless it is a project that has been done repeatedly over many years in the organization. Furthermore, continuous process improvement and monitoring is not done enough even in organizations that declare achievement of higher levels of CMMI. Our team had subsystems that overran their initial estimates by over 100%, causing nearly a year in delay. However, there were basically no penalties or major process changes despite the fact that multiple subsystems overran estimates multiple times. Process professionals, engineers, and managers are simply not aggressive in tackling these problems. In addition, estimates tend to come from individuals. I imagine that a more collaborative team-based estimation approach would be better, factoring different levels of experience and sharing the burden of making estimations realistic. Also, recorded estimates need to be coupled with recorded justification.
- rahoulb 15y agoagreed. we don't have a language to define the problem in the first place. i am great at estimating - unfortunately i often go over because what i heard was being asked for is subtly different to what the client thought they were asking for
- charlief 15y agoLt. Commander Geordi La Forge: Look, Mr. Scott, I'd love to explain everything to you, but the Captain wants this spectrographic analysis done by 1300 hours. [La Forge goes back to work; Scotty follows slowly] Scotty: Do you mind a little advice? Starfleet captains are like children. They want everything right now and they want it their way. But the secret is to give them only what they need, not what they want. Lt. Commander Geordi La Forge: Yeah, well, I told the Captain I'd have this analysis done in an hour. Scotty: How long will it really take? Lt. Commander Geordi La Forge: An hour! Scotty: Oh, you didn't tell him how long it would really take, did ya? Lt. Commander Geordi La Forge: Well, of course I did. Scotty: Oh, laddie. You've got a lot to learn if you want people to think of you as a miracle worker.
- jdavid 15y agoThis might work in StarFleet, but the problem is that if you promise a manager something repeatedly, by overestimating, they will start to assume you are padding your results. Having worked on scrum teams before, I find its a good structured way to have a dialog about how much work is left, and how long you expect it to take. So rather than saying an hour. You would say this is as easy as changing a diaper, or its as hard as navigating through an asteroid belt at the speed of light ( having or not having done it ). I would appreciate it if managers ask: Have you done this before? (yes, no) How similar is this to something you have done before? ( very similar, kinda similar, totally new ) What concerns you about the task, or what risks do you see coming your way? ( detailed answer ) What can I do to get you the resources you need to help you deal with the risks you can foresee now?
- ThomPete 15y agoOnly when scrum is extended into the overall strategy of the company can it solve that problem. It makes no sense if only the developers and designers are doing scrum when the rest of the company is expecting deadline deliveries.
- zedshaw 15y ago> the problem is that if you promise a manager something The real problem is thinking of "estimates" as "promises" when really they're rough guesses. If you go around holding people to a guess as if it were some kind of gospel biblical contract then yes, they will lie their ass off to protect themselves. Combine that with the fact that most organizations attempt to control the platform used, computers used, monitor size, operating system, IDE, editors, revision control tools, languages, documentation systems, testing methodology, meeting requirements, pairing, and nearly everything they can, and you start to see the real problem is.... managers who don't know programming, motherfucker. :-)
- k7d 15y agoThat's why we were using complexity estimates in points (say 1 to 5) instead of actual time estimates in my last startup. Once you have some worklog, it's easy to calculate how many points the team can get done in a week (or whatever your estimation cycle is). This little abstraction made estimates much more reliable. I guess some "agile" methodologies propose a similiar approach, but we didn't really follow any specific one, just figured out what works best as we moved along and kept the process as lean as possible.
- hammerdr 15y agoJust to clarify what k7d is saying when he quotes "agile" methodologies: Any prescriptive agile methodologies (first, do X. then, do Y) are really antithetical to agile. True agile processes are exactly what his own startup did. They used what worked. They implemented a practice (complexity points) that was relevant to their principles (accurate estimation). Of course, you should also be tweaking your process as you go along.
- 5l 15y agoThere's another way as well; specify a range of time within which you expect the task to be completed. This also communicates your uncertainty about the estimate at the same time.
- hammock 15y agoThe author makes the point nicely at the front: "because the nature of the work is creating." I'm not a developer but I can confidently say that it's not just developers - NO ONE can estimate time when it comes to creative work. I use the term creative loosely, it could be anything from developing a business strategy, to crafting a story, to art directing an original visual, to writing code for a novel problem. The problem is the same one that makes it difficult to say "when will we have a cure for Parkinson's," "when will we have fusion power," "when will we discover a viable alternative energy"? You often see estimates like 20 years, 40 years, 50 years - but properly interpreted, these aren't actual estimates of the amount of time it will take, but rather like a proxy for a much more probabilistic, uncertainty-oriented notion.
- ashleymoran 15y agoHi hammock, thanks for the comment (I'm the author). For some reason you've reminded me of the motivation factors Dan Pink talks about. I wonder if trying to commit to estimates makes our creativity degrade in the same way as paying cash bonuses? http://www.youtube.com/watch?v=u6XAPnuFjJc http://www.youtube.com/watch?v=u6XAPnuFjJc
- jospehcanto 15y agoWant to hire the most experienced programmer out of a group of candidates? Ask them to estimate a programming task, then pick the one that gives the longest estimate.
- netghost 15y agoI'd say hire the one that gives you the best justification for their estimate. It's important for people to understand what is and is not involved in an estimate as well as why they think something is hard. Once you communicate that, you can uncover a lot of potential problems and misunderstandings. For instance just the other day my co-worker was asked to estimate a task that seemed to our boss to be pretty small. He estimated it as being 2-8 days, it wasn't until they actually started talking about _why_, that they both agreed on the requirements. The resulting task will probably take 1-3 hours. So sure, as a developer learns more they may estimate tasks as being longer, but communicating your assumptions is more important than throwing out huge estimates to cover your ass ;)
- RyanMcGreal 15y agoThis: > It's not just developers that are bad with estimates either. Everyone at some point is just winging it because it's something they've never done before and won't be able to successfully make a judgement until they have. When my manager asks, "How long will this take," about half the time my honest answer is, "I don't know."
- HeyLaughingBoy 15y agoBut from your manager's perspective, you probably do know. You know if it will take more than or less than a year. You know if it will take more than or less than a month. You have some idea of what needs to be done. You have some idea of what parts of it you don't know, etc. One of the most important things I've learned about estimating is first asking how accurate an estimate is needed. Often the person just wants to know "can I have it tomorrow, or will it take 3 months?"
- anthonyb 15y agoDepending on the task, it might not actually even be possible. Or, it's doable but not without rewriting major libraries or buying hundreds of servers.
- HeyLaughingBoy 15y agoAnd all those things you've just said are valuable pieces of information to the person asking!!!
- michaelcampbell 15y agoThere are 2 sides to this, one of which is detailed in most comments below, and I see it from a lot of devs I work with but mainly the less experienced ones, and that is the eternal optimism issue. That's been covered a lot already, so no point in belaboring that. The OTHER side is that, at least given my experience in the financial software domain, managers don't WANT accurate estimates. They absolutely abhor them. And developers are punished for giving them. So they aren't given. An accurate estimate, such that one can be made, is usually around a 70%-80% confidence interval. It includes many specifically unforeseen, but generally known issues such as problems with the environment, lacking specifications and time required to get them, including "making $#@! up" fudge factors, technical hurdles, cogitation and exploration time, etc. But managers can't hear that. All they want to hear is something they can sell to their superiors, which is often the customer. An accurate estimate is almost always going to be larger than that, so they won't accept it. So, the development staff is forced to skimp on quality or features to make an artificial date. But that's ok! Why? Well, it's partially an organization's willingness to accept "there's never enough time to do it right, but there's always enough time to do it twice" (or more), but that's not even half of the issue. The larger part is that NO ONE WANTS IT RIGHT THE FIRST TIME. I've seen this time after time. It's a win/win to provide sub-par product. Why? It makes a manager look great to give low estimates (win), hold the developers to that, and deliver a product with less-than-promised quality, or scope, or both. That provides customers something to gripe about (which EVERY customer wants; it makes them appear "tough" or "thorough"; win), and it gives the managers something to "fix" and appear reactive to the customers' needs (win). Who's holding the bag for all this win? The devs, and support. There are inevitable promises of being able to go back and fix things, but that never happens; once something is in production, no matter how crappy, it has the almighty momentum. If it's "working", almost no matter how fragile it is, there's no appetite to change something that works so that it can work better. That provides no revenue, and does impart considerable risk (with limited or no QA, having moved on to the next thing) and/or cost (keeping your QA around to regress fixes). Although that mindset infuriates me, I don't honestly know that it's not the best way. It seems to have evolved, and companies that do it seem to do ok, so maybe it's the Darwinian process at work.
- dennisgorelik 15y ago
- ThomPete 15y agoTime estimations is an industrial way of thinking applied to a post-industrial world. In the post industrial world time isn't the problem but rather project definition and scoping. In the industrial world the problem was already solved (machine was built, market often established and output depended on a few factors that could be adjusted. Need more output add more of X) In the post industrial world every project is about problem solving and scoping. To put it into comparison. If we apply post-industrial thinking to an industrial world. It means that each time a product needed to be done if not the factory, then the machines would have to be developed. It will take many many years before time estimation will die, but it will happen.
- diegob 15y agoWhat could replace it?
- bartonfink 15y agoA serious attempt to provide a precise, correct answer to the ? "What do I really want done?"
- diegob 15y agoSo things like prototyping, UML, use cases, and Agile were not a "serious attempt" to answer that? I think it's also unwise to tell your manager "it'll be done when it's done."
- deleted 15y ago[deleted]
- ThomPete 15y agoYou know there is a saying in the creative industry when project managers come knocking on your door. "You want it know, or when it's done?" My personal experience is that most deadlines are primarily perceptual.
- DanielRibeiro 15y agoBecause not all of them read Agile Estimating and Planning[1] [1] http://www.mountaingoatsoftware.com/books/1-agile-estimating-and-planning http://www.mountaingoatsoftware.com/books/1-agile-estimating...
- iaskwhy 15y agoWhen I needed to estimate a new project at my previous job I used to pretty much always say "3 months". I made sure clients knew I was talking about a MVP even if they were thinking about making something like Microsoft Excel in-house. Then we would just build on top of that, one block at a time, never more than 3 months for each block.
- larsberg 15y agoI'd say that people can't estimate time because it's an acquired skill and most people don't try to acquire it. When I managed a team, I had people put their initial estimates in the tracking tool, and when closing out the item they'd also fill in how long it actually took. Then, some of the report generation tools would let them see how accurate they were. There were no review metrics associated with being accurate, but I found that within a couple of months in a new area, individuals started getting much more accurate without just lamely padding out schedules (their teammates would have called them out, and even I wasn't pointy-haired enough to be fooled that easily). An unexpected bonus is that people also got a lot better at describing their work and investigating the risky bits before throwing something onto the schedule for the sprint. But, we didn't do this for purely investigative or experimental work (i.e. "try out a new immutable text region design in the editor"). We'd just timebox work like that and evaluate progress to decide whether to keep going or not.
- HeyLaughingBoy 15y agowhen closing out the item they'd also fill in how long it actually took Excellent idea. We do this and it really works well to see how far off your estimates were. Feedback is essential to controlling any process!
- br1 15y agoI can't stand the rubbish advise to 'just double the estimate'. It just means you'll get an estimate 2^n times the size of the original guess from the guy n steps away from you.
- jdp23 15y agoWait a second. In the right environment, good developers can estimate time fairly well on most things, even for tasks they haven't done before. I'm as prey to the "eternal optimism" factor as anybody else, but it's easy enough to work around: start by doubling your own estimate, and over time learn what multiple is right for you.
- PaulHoule 15y agoA big part of the problem is that management often isn't interested in honest estimates. You can certainly find better practices in some organizations, but in many organizations, a certain team gets tasked with completing a certain assignment by an arbitrary deadline and no attempt is made to reconcile the triple constraints with reality. In a context like that, developers may not be asked to make estimates, and if they do make estimates they don't believe that they'll be taken seriously. So they never develop the chance to learn how to estimate. The accuracy of estimation also depends on the context. If, for some reason, I had to fix a difficult-to-reproduce bug in a large system written in COBOL that runs on a mainframe, I'd have very little idea of how long it would take me to learn COBOL, understand the codebase, figure out the tools, and track the problem down. A COBOL jock would obviously do better. On the other hand, I've worked on greenfield well-specified business CRUD apps based on a correctly aligned framework where I could estimate that something would take 21.25 hours and I'd really get it done in 19.75 or 22.50. I've met developers who will absolutely refuse to estimate anything but I think more often developers don't believe their estimates will be listened to. The good news for both developers and managers is that estimation is a learnable skill. If you get in the habit of making estimates and testing them, you'll get better amazingly fast. See the classic book http://www.amazon.com/Software-Estimation-Demystifying-Practices-Microsoft/dp/0735605351 http://www.amazon.com/Software-Estimation-Demystifying-Pract...
- Natsu 15y ago> The good news for both developers and managers is that estimation is a learnable skill. If you get in the habit of making estimates and testing them, you'll get better amazingly fast. See the classic book It's not hard to learn to make reasonable estimates. Even for unknown problems, I can often say that X has usually taken about Y time in the past and be right most of the time. The real problem comes when the estimate you give is not the one management wants to hear.
- redthrowaway 15y agoOr when you're tasked to do something you've never done before, and your initial thoughts of "I bet y is like x" turn out to be terribly wrong. Something so seemingly trivial as a different API can make two similar tasks take vastly different amounts of time, especially if you're approaching the second problem with the mindset induced by the first API.
- sunchild 15y agoIt is always a mistake to ask: "how long will this take you?" I've spent my career as a lawyer dealing with this problem. The solution is to choose a price that represents the value proposition of the output (whether it's code or contracts). As part of that price, you will bring a comprehensive process to the table – one that is very clear about what the client is expected to provide. I have gathered a huge amount of timekeeping data from lawyers, and crunched it up, down, left, right and center over the years. Here is what I learned: 1. If a task can be defined, it has a predictable price. 2. Tasks should not be measured by how long they take start to finish, but rather by how much time is actually required to complete them. 3. A clearly defined task always takes just about the same amount of time. The start to finish time is variable because: (a) the client is faster or slower at providing resources or information; and (b) your other client work is causing bottlenecks in your own availability. 4. You can solve for (a) and (b) above. I'll leave it to your imagination how. That's my secret. ;)
- joezydeco 15y agoBecause estimates are not committments. http://cwd.dhemery.com/2003/08/estimates_are_not_commitments/ http://cwd.dhemery.com/2003/08/estimates_are_not_commitments... "If you ask Fred, “When will you be done?” have you asked for an estimate or a commitment? What does Fred think you asked for? If Fred says, “Two weeks from today,” has he given an estimate or a commitment? What might happen if you want a commitment and Fred thinks you want an estimate? What might happen if you want an estimate and Fred thinks you want a commitment? How could you make it crystal clear whether you’re asking for an estimate or for a commitment? How could you make it crystal clear whether Fred is giving an estimate or a commitment?"
- nlawalker 15y agoOh man oh man, this right here. I like to think of myself as someone who has a lot of common sense, but reading McConnell's "Software Estimation" made me feel like an idiot. He lays out the most important stuff right at the start of the book: an estimate is not a commitment is not a plan to meet a target. Reading this, I realized that where I work, the term "estimate" is often used to mean any one of those three things at different times, but most often is used to mean "commitment." Not knowing any better, I fell right in line. McConnell's basic strategy for delivering an estimate (give a minimum, a maximum, and an "expected time") is great for so many reasons, but the reason I like it the best is for its communication value - by giving three numbers, none of them being an "I can have it done by..." number, you reinforce the idea that you are delivering an estimate and that the point of delivering that estimate is to help the project manager control the project. If it turns out that the PM is lazy and they really do just want a commitment ("sure, sure, whatever, when will it be done?!"), you can adjust your communication strategy accordingly.
- d4nt 15y agoPure coding is easy to estimate accurately. If you asked a developer to estimate how long it would take to hand write a class for every HTTP status code in v1.1 of the standard (and gave them a copy of the standard), they could probably give you an accurate figure. Of course, most development projects are not like that. The pure coding part of it is interspersed with countless decisions about how the app should work, with each decision requiring input from lots of people, plus a bit of experimentation and rework. The process of getting to a decision is hard to estimate and the amount of development that each decision will create is impossible to know until the decision has been made. Estimating a software project is like estimating the length of time it takes to get a law passed. It's not a computer science or even an engineering matter, its a political/ psychological one.
- kragen 15y ago> If you asked a developer to estimate how long it would take to hand write a class for every HTTP status code in v1.1 of the standard (and gave them a copy of the standard), they could probably give you an accurate figure. Yes, but that's explicitly demanding that they write the software incompetently. Writing software incompetently, by mechanically carrying out actions that ought to be automated, is easy to estimate. But if I thought I needed a Java class for each HTTP/1.1 status code, I'd write a Perl script to generate them, be done in a tiny fraction of the time, and have a vastly more maintainable codebase. Your other point about multiple stakeholders is well taken, of course. But even when it comes to solving a well-defined problem, it's easy to misestimate by orders of magnitude.
- NY_USA_Hacker 15y agoOnce a developer has done a project, he can give a good estimate of how long it would take for him to do that project again! Really, it's easy for developers to estimate time much the same way plumbers, carpenters, auto body shop workers, general contractors, dentists, etc. do: When a developer has done a very similar project more than 10 times recently, they can give a good estimate for how long it will take to do the project once more. This situation is quite general in engineering and other work of wide variety. Similarly, in general, when some project is being done for the first time, with no prior experience with comparable projects, then time estimates are tough to give. In particular, for 'developers', now they work heavily with 'parts, pieces, and tools' from others, and working with these for the first time encounters standard problems: (A) How to use the parts, etc., needs good documentation rarely available. (B) Newer parts, etc. commonly have strange behavior or actual bugs that have to be encountered, diagnosed, and worked around. So a developer does not know how much time will be spent mud wrestling with (A) and (B).
- anthonyb 15y agoExcept that no two projects are ever really the same. Even with a very similar project you'll have different people, different systems to interface with and different scope. Plus, any developer worth their salt will have built libraries as they went (or documented the existing ones), so the next similar project will take much, much less time.
- planetmcd 15y agoTime is not a fixed unit of measure. I may be going closer to the speed of light than a project manager, so one week to me, might be like 5 years to them.
- tincholio 15y agothis: http://en.wikipedia.org/wiki/Hofstadter%27s_law http://en.wikipedia.org/wiki/Hofstadter%27s_law
- pmb 15y agoBecause they are doing something that has never been done before. The unknown is exactly that - unknown. You can make guesses, but they will never be anything but guesses until the problem has been solved a few times. However, once a problem is solved, it does not need to be re-solved, and so the attention of the company turns to a new unknown problem.
- knodi 15y agoI find that only bad managers ask "how long will this take you?" and idiot manager will take what ever time you give them and try to cut that short or judge time for the developers or engineers; like "this should be easy and will only take few day". Good manager that have "developed" before will ask "how much work is left?" and "What are some of the out standing problems that need to be resolved?" Look for the good ones avoid the idiots.
- Natsu 15y agoYou're right that managers who understand your job can make life a lot easier. But this goes both ways. I find that understanding what constraints my management is under can help me to help them plan. When you understand what their problem is (e.g. we promised X to the client and we have to make it work somehow), you might be able to rearrange things to make that possible. Of course, an ounce of prevention is worth a pound of cure: if you can help them avoid promising the impossible, you'll be a lot better off. Otherwise, you end up suffering due to arbitrary deadlines created for the sake of looking good. If you can find better ways for your boss to look good than impossible deadlines, you'll be way ahead. I grant, though, much of this is easier said than done.
- knodi 15y agoVery true and there is a very easy way to do this. Be your own boss. lol
- rch 15y agoIt is easier to estimate time for repetitive tasks, and (ideally) programming is not a repetitive task. once something becomes predictable, it is probably also script-able.
- dpcan 15y agoIt's because programming is as much an art as it is a science. You don't ask a painter how many hours it will take to complete a masterpiece. Nor do you ask a composer how long it will take to write the next great hit. Or an author how long it will take to finish a great book. Sure, we can ask an artist to be done by "next Tuesday", or in 20 hours. And the artist will say, no problem, but there is no guarantee of quality. Programming is no different. Yes, there is a method, a science, to getting things done, but when it comes to creating a finished work of art, it is not a time oriented task. If you want quality, don't put us on the clock.
- clawoo 15y agoFrom an older Slashdot comment on the subject: I multiply all time estimates by pi, to account for running around in circles.
- Hominem 15y agoI am asked to give estimates all the time, sometimes based on something like "A guy down the hall says it crashed, how long will it take you to fix." or "Bob wants a portal site". So I've come up with a method that works for me. Add together hours based on what things I will need to fiddle with to get it to work. •Involves strange business practice I will have to figure out or gleen from area experts +5h •I didn't write the code +5h •Involves something like wcf or msmq +3h •It is a "it is too slow" bug +3h •Involves stored procedures +2h •Involves 3rd party UI component +10h and so on, and so on.
- MartinCron 15y agoI am great at estimating time. I can tell you within 15 seconds plus-or-minus how long it will take to copy files from one server to another. That's where any valid comparisons to construction or manufacturing end.
- nlawalker 15y agoI think the main thrust of the article is factually correct (you can't estimate the creation of something new), but I don't think that's a very satisfying answer because you can't do anything about it. In my opinion, the single biggest problem with developers doing estimates is that they think they're being asked for a commitment, or they are being asked for a commitment but the asker is calling it an estimate. This creates a large number of problems in expectations and communication, and it causes the whole project to break down. There are some things that can be done on a project to help improve communication about estimates, commitments and targets: - Ensure that estimates, commitments, and goals are understood to be three separate things. - Ensure that everyone knows the benefits and uses of estimates, commitments and goals, as well as the non-uses. This is doubly true for estimates: many people treat them as commitments, but in reality they are supposed to be indicators that can be used to help control a project and make it successful. - Encourage people to put effort into their estimates. Developers often don't like working on estimates because every minute they spend working on them (or on other stuff like timesheets and status reports) is a minute they could have spent thinking, designing and coding. Ensure that everyone knows that spending time on estimates and other activities is truly valuable to the project and the group, and helps ensure success. - Do everything possible to remove stress and pressure around estimates. Reinforce the idea that estimates are used to help steer the project to success, not to hold peoples' feet over the fire (if a PM is trying to shrink estimates or pointing to estimates after a project has started and saying "tasks x, y and z are late," they're doing it wrong). - Make it known that estimates are supposed to have some uncertainty. Don't accept or expect single-point estimates, and make sure the people delivering the estimates aren't pressured to do so.
- richieb 15y agoWhich part of the meaning of the work "estimate" are we missing: "an approximate judgment or calculation, as of the value, amount, time, size, or weight of something." ??
- patja 15y agoDeveloper estimation improves when the developer is estimating the time for a task that is repeatable and they have experience or data on how much time the task took in the past. Substitute any title for "developer" in the previous statement and it remains true: civil engineer, drywall installer, plumber, etc. The challenge is that relatively few developer tasks are highly repeatable, and very few developers are disciplined about collecting data on how long similar tasks required in the past. Also high performing developers get bored easily and frequently want to chase the new shiny tool/framework, where they have no past experience or data to rely on for estimating. A first question in asking a developer about their estimate is "have you done this type of task before with the same technology you are planning to use". If no, disregard any estimates. You can get good estimates for high volume of task teams, like maintenance or break/fix teams where the technology remains relatively static from one work iteration to the next, and the work items can be bucketed into meaningful and consistent sizes (T shirt sizing or what have you). Those are typically where you have your junior (or offshore) developers staffed as they pay their dues, and they can benefit greatly from having discipline around collecting data on their actual experience and using that data to reduce variance in estimates vs actuals in the future. This is also a great space for a new dev lead or manager to cut their teeth on managing the consistent collection and application of this data to reduce variance to plan. For the really fun work though, where your high performing developers want to be operating so they can thrive and experience self-actualization (see Maslow), forget about the estimating angst and just timebox them or go agile -- build something, release it, refactor it, repeat. Don't waste your time creating the illusion of certainty about the future when you have nothing but optimistic gut feel as input to the estimating machine.
- michaelpinto 15y agoBecause most developers are optimists and because most clients don't think they'll need any changes...
- mbesto 15y agoThis goes for everything in life. Humans suck at planning. EDIT: http://book.personalmba.com/planning-fallacy/ http://book.personalmba.com/planning-fallacy/ “Hofstadter’s Law: it always takes longer than you expect, even when you take into account Hofstadter’s Law.” — Douglas Hofstadter, cognitive scientist and Pulitzer Prize–winning author of Gödel, Escher, Bach: An Eternal Golden Braid
- bugsy 15y agoAccurate estimation is certainly possible and is practiced by professionals, I do it myself. It's a skill though and it requires ground work in advance. Those interested may find discussion of some methods in McConnell's "Software Estimation: Demystifying the Black Art". Humphrey's PSP materials are an earlier but useful source of information. The skill is irrelevant in most workplaces though. In most cases time to do an estimation is forbidden, and in the rare cases where an accurate estimation is produced, it is replaced with management's wishful-thinking estimate instead, which insecure developers are often strong-armed into "agreeing" to. Replacing an accurate estimate with wishful thinking and whipping the slaves to go faster does not mean accurate estimates are impossible. It means that there is a problem with endemic management incompetence and unprofessionalism throughout this industry. If you have not established a track record of accurate estimates, you shouldn't be managing in any capacity at all. I don't expect this to happen though. I fully expect incompetent unprofessional management to continue to be the rule throughout most of the industry because there is little sincere interest in fixing things compared to maintaining empires ruled by fools. The preferred system is of blaming developers for bad estimates that were forced upon them by management, or that were produced by people who have no idea how to estimate and who are given no tools or training in how to do so. What a relief it is not to be working for such incompetent management and be on my own. To those whose bosses are bullying them into giving bogus estimates and then blamed when things go wrong, you have my sympathies.
- kragen 15y agoWhat do you think of my points in http://news.ycombinator.com/item?id=2425838 http://news.ycombinator.com/item?id=2425838 about automation? It sounds like you disagree with them but I don't understand why.
- motters 15y agoThe problem is that most software development is novel, so there are zero previous data points from which estimates can be derived.
- SpaceAcer 15y agoClassic line... the better question is: "Why can't developers see into the future?" Programming is one of the worst jobs for dealing with people. Managers assume you have no life and work you 12 hours a day for a software product, telling you that it might save your job. It's all a ruse; once they get what they want, why pay for an expensive developer to support your new site or application? If anyone asks me if they should be a professional developer I tell them 'Run away!'. I don't wish the experience on anyone.
- madaxe 15y agoEstimates are unimportant. Why? Because most conversations about estimates go thusly: Client: "How long will it take?" Dev: "Approximately three weeks." Client: "We need a firm date." Dev: "Fine, April 29th." Client: "Unacceptable. We require this functionality by April 10th." Dev: "I could only possibly do it by April 10th by having the entire team work day and night until then." Client: "Excellent. We look forward to launching on the tenth." And then, they're pissed off when you pull off the incredible and deliver a three week build in three days. Fuck everything about this business.
- scotty79 15y agoI have a maze drawn at this A4 sheet of paper. How long it will take you to get out of this maze?
- known 15y agoYou cannot estimate debugging time.