It can be a little later. Your requirements is like demanding nobody can buy a house unless they have pay they entire amount upfront.
by postalrat 12d ago
It can be a little later. Your requirements is like demanding nobody can buy a house unless they have pay they entire amount upfront.
- AndrewDucker 12d agoPeople do not believe big companies when they say "I'll deal with the externalities a little later."
- triceratops 12d agoSo then does the data center compensate local residents for their higher power bills today? Until the new capacity comes online? > Your requirements is like demanding nobody can buy a house unless they have pay they entire amount upfront. No it's like demanding your new neighbors aren't forced to lend you money for your purchase - which is entirely reasonable. If you need money, get it from the bank. The top-level comment explains it already: "When you drop a data center into an area, energy prices will spike. Additionally, without that green energy capacity they will cause much more air pollution."
- no-name-here 12d agoIt typically takes 11-12 years for a nuclear plant to get built including planning and construction [1]. Is the idea that we'd build the data centers now, and finish the nuclear plants to power them 11-12 years from now? https://www.researchgate.net/figure/Typical-timeline-of-a-nuclear-plant-construction-and-start-up-project-Source-IAEA_fig5_304660691 https://www.researchgate.net/figure/Typical-timeline-of-a-nu...
- leonidasrup 12d agoFor wind turbine project from design and planning to operational use-takes approximately 4-7 years. An offshore wind turbine project requires about 7-10 years. https://jmhpower.com/how-long-does-it-take-to-build-a-wind-turbine/ https://jmhpower.com/how-long-does-it-take-to-build-a-wind-t...
- triceratops 12d ago> For wind turbine project from design and planning to operational use-takes approximately 4-7 years. That's still better than 11-12 years. How long does a solar farm take? If residents' opposition is rooted in higher power prices, data centers could just pay extra instead until the new capacity comes online. Seems like a cheap way to pay off opposition. > An offshore wind turbine project requires about 7-10 years. Given this article is about Pennsylvania, it'll probably take millions of years.
- leonidasrup 12d ago> How long does a solar farm take? 24–48 months, but for a data center that has to run 24/7 you need to also build a gas power plant. https://www.pvfarm.io/blog/utility-scale-solar-project-development-stages https://www.pvfarm.io/blog/utility-scale-solar-project-devel... https://globalenergymonitor.org/research/betting-big-data-centers-us-now-leads-world-new-gas-power-development https://globalenergymonitor.org/research/betting-big-data-ce...
- triceratops 12d agoOr use batteries. Also residential and industrial use will be lower at night. So the existing grid supply may also be enough.
- leonidasrup 12d agoIn many places the contraty is true, peak electricity prices are after sunset, during night.
- triceratops 12d ago> peak electricity prices are after sunset The famous evening duck curve, when people go home and cook and turn on heating/cooling appliances. California is able to flatten that out with batteries alone. https://eticaag.com/battery-storage-and-the-duck-curve-march-29-event/ https://eticaag.com/battery-storage-and-the-duck-curve-march... > during night When everyone's asleep? Serious doubt, please show your sources.
- lenkite 10d ago> It can be a little later. Your requirements is like demanding nobody can buy a house unless they have pay they entire amount upfront. Have data center companies mortgaged their property to the public and paying interest on "power loans" monthly ? Please correct me if I am ignorant.