I worked with a non-technical manager (banking background, somehow wormed his way into managing development) who never asked devs what they thought a task would
by klancaster 7y ago
I worked with a non-technical manager (banking background, somehow wormed his way into managing development) who never asked devs what they thought a task would take. I finally convinced him that this could not possibly work. I sat with him the first time he asked a dev how long the current task would take. The dev said "4 weeks". This guy said "I think it should take 2, so that is what I am putting in the schedule". Mind you, this guy had never written a line of code and had NO basis for his "thought" on the task length.
- _def 7y agoHaha that's great. "Let's settle with 3! Ha, good deal." Things like these make me sometimes think that the whole business world is just a bunch of people lying to each other. Very depressing.
- wikiman 7y agoMy personal favorite are the bosses that poll the group and pick the lowest estimate